Hey Guys:
Although I love the auto-leveling features, I very much rather user my own manual leveling. Helps with resouce allocations.
Anybody knows how to do that in the resouce view ?
Greg Titus
2006-07-28, 12:41 PM
Anybody knows how to do that in the resouce view ?
In the upper-left corner of the timeline is a little gray box, which both needs a new icon and needs to have the cursor turn back into an arrow instead of a left-right resize cursor when you are over it. Thus it is unsurprising that you didn't find it. :-)
Anyway, click on that icon to turn on resource usage graphs, which will show you the times at which each of the selected resources is overloaded.
anmar
2006-07-28, 12:57 PM
Cool:
I like it. the icon is pretty good and the feedback is ideal. However, this still does not answer my questions. What is I have two tasks assigned to the same resource. I usually do a dependency (leveling dependency) between them. in OmniPlan, all I can do is press the auto-level button. but I want to do a Manual Leveling.
I tried adding predecessor in the task inspecto but it was greyed out due to not being in the gant chart view.
Any ideas ?