View Full Version : Converting task to milesone (and visa versa)
vmarco
07-28-2006, 02:50 PM
Is there a way to convert a task to a milestone? and visa versa?
I am not finding it.
Thanks,
Vince
Lizard
07-28-2006, 07:54 PM
Select your task (or milestone) in the task view.
In the task inspector, see a drop-down which currently says "task" (or "milestone").
Switch it to the other one.
(Note that switching a task to a milestone will drop information about duration, end date, assigned resources, etc. These cannot be restored just by changing it back to a task.)
vBulletin® v3.7.2, Copyright ©2000-2008, Jelsoft Enterprises Ltd.