View Full Version : Bug: Assigning partial resources


ajrichardson
08-01-2006, 01:10 PM
Hi-

I just tried assigning two resources each to a task at 50% each, and it made the task (apparently) infinite in duration. Switching one of them to 25% made it return to its proper size. Removing one of the resources also normalized again.

Adam

michaelklouda
08-01-2006, 02:15 PM
I find that clicking on the assignment icon on the navigation bar does not always display the list of possible resources. I often need to click several time to see the drop down.

ajrichardson
08-01-2006, 02:23 PM
I get this too, it's annoying. Only about 25% of the time does the menu drop like it should, no matter where on the icon I click.

Adam