View Full Version : Bug: Problem with changing work schedule


abusch
2006-08-02, 02:01 AM
Trying to change the work schedule for a person (inserting two days of non-availability in a specific week), I run into problems and cannot alter the schedule. (By the way -- how is one supposed to do this? I do it with the mouse, dragging the end of the week to shorten it and then add another day).

The error message is "[NSCFArray insertObject:atIndex:]: index (2) beyond bounds (1)"

Nat
2006-08-02, 10:16 AM
I have the same problem... Moreover the central calendar differ from the one on the bottom left.
nat

Brian
2006-08-02, 10:37 AM
The error message is "[NSCFArray insertObject:atIndex:]: index (2) beyond bounds (1)"