I want to create tasks and assign them to a resource. These tasks are not dependent upon previous tasks being completed, but they cannot be performed at the same time. Is there some way to accomplish this? I want OmniPlan to know that the tasks cannot be performed simultaneously, and show warnings when they are overlapping. Is there something obvious I'm missing?

Lizard
2006-08-03, 01:44 PM
After you've set up your tasks and resources and assigned tasks to resources, level your project (in the toolbar or Project menu).
To quickly see if your project is in need of leveling, turn on the resource utilization graphs in the resource view (click the button that looks like the attached image). Green means people have a full load, blue means they have some free time, and pink means they're overloaded.