There are two parts to this request.
As a project grows in size (the file I am working with now has 1304 lines it the contents.xml file). The overall performance of the application drops significantly. As I type in the task or comment field, the utilization of the appliation can go to 74% of the CPU (Running on a 2.0Ghz Imac with 2GB memory - not much else going on on the system at this time). The responsiveness is so slow that is a bit of a bother

Linked Projects - I may have sent an email about this, but here is a fuller explanation. I sometimes have several sub-projects and my management does not want all the detail (yes I know one can collapse portions). What I would like is to be able to link all or a portion of several different tasks into another summary project. Obviously there will need to be an update/refresh function -- most of the time it will be automatic on file open.