what is a lead time please?

I got several examples of task wich should begin two days after start or begin of another task.

Is that the way of using the lead time?

skwirl
2006-12-13, 01:00 PM
You've got the right idea. Lead time is extra padding between tasks.

If you want to set up a task that is a dependent or a prerequisite of another task with a bit of lead time, go to the "Task : Dependencies" inspector and enter the the time value in the "Lead Time" field.

Lizard
2006-12-13, 01:18 PM
Yes, exactly. You want to create a Start->Start dependency with a Lead Time of 2 days.