View Full Version : Showing total resource cost for task groups?
docswab
2007-01-04, 11:42 AM
How do I view the total resource cost for all the child resources contained in a Task Group?
If this is not possible now, it seems like an important feature to add ASAP.
Thanks,
Steve
skwirl
2007-01-04, 01:54 PM
You can turn on the cost columns by going to "View" --> "View Options" in the menubar and checking the "Resources Cost", "Total Cost", and "Task Cost" boxes.
docswab
2007-01-04, 02:00 PM
Thanks for your speedy reply. I had found it myself and tried to post my own reply, but it must not have been saved.
I appreciate Omni's great support.
Steve
mysvcmon
2007-01-04, 02:02 PM
just started w/ the product....having some issues getting my numbers to add up with multiple resources on a task at different rates...
Lizard
2007-01-04, 04:03 PM
mysvcmon: Could you please provide a specific example?