View Full Version : tracking PM time for project duration


plots
2007-03-09, 03:24 PM
At my company, the project manager is usually working on 2-3 projects at a time. I'd like to be able to track this on the individual project plans.

I'm thinking I could create a single task "Manage Project" and assign the PM to this at 30% (or whatever). Is there a better way?

How would I make this task run the entire duration of the project, even as the duration may change? For example, if the project is late by 2 weeks, this adds 2 weeks of the developer, plus 2 weeks x 30% of the PM, something like that.

Thanks for your suggestions.

akwong
2007-03-14, 03:39 PM
At my company, the project manager is usually working on 2-3 projects at a time. I'd like to be able to track this on the individual project plans.

I'm thinking I could create a single task "Manage Project" and assign the PM to this at 30% (or whatever). Is there a better way?

How would I make this task run the entire duration of the project, even as the duration may change? For example, if the project is late by 2 weeks, this adds 2 weeks of the developer, plus 2 weeks x 30% of the PM, something like that.

Thanks for your suggestions.

You could do that. If the project was late by 2 weeks, you would have to manually change the duration of the task your PM is assigned to.

Another method would be to simply set your Project Manager's units to 33.3% in the Resource view for all 3 projects. The downside to this is that you don't actually "see" the Project Manager working on a task, you just know that 66.6% of his units are devoted to other projects.