View Full Version : Changing a Project to a Single Action List
Dogsbreath
2008-02-02, 04:54 AM
It's probably being a new user, but I seem to keep setting up projects where I should have set up a single action list.
Short of doing a copy and paste into a newly created single action list, is there any quicker way of doing this?
ptone
2008-02-02, 06:48 AM
select the project then open the inspector (blue circle with "i")
-P
Dogsbreath
2008-02-02, 07:38 AM
This only seems to give you the option to change it to On Hold or Dropped. Never mind, I wasn't hopeful. Thanks.
jpkunst
2008-02-02, 10:44 AM
Look again, with 'Project' selected in the inspector: above the row of buttons for Status (Active, On Hold etc.) there is a row of buttons for Type (Sequential, Parallel and Single Action List (the shoebox icon)).
JP
Dogsbreath
2008-02-03, 09:08 AM
Ah ha! I just cleaned my glasses and not a moment too soon by the looks of it!
Thanks a lot both of you.
vBulletin® v3.7.3, Copyright ©2000-2008, Jelsoft Enterprises Ltd.