PDA

View Full Version : Refreshing views


myotis
2008-02-04, 07:21 AM
When I change the due date for an existing task, how do I refresh the view so that it jumps to the right place in Due hierarchy view.

eg so it moves from the due today view into the due within the next three months view.

Thanks,

Graham

Toadling
2008-02-04, 11:44 AM
Don't have OF in front of me right now, but I think the Clean Up command (Command-K or use the purple broom tool bar button) will take care of this for you.

myotis
2008-02-04, 12:41 PM
Don't have OF in front of me right now, but I think the Clean Up command (Command-K or use the purple broom tool bar button) will take care of this for you.

Thanks, but, unfortunately, already tried this, and it didn't work.

Some time later..... it now seems to be auto updating, which is what I thought it was doing before, but it hasn't been, yesterday and today !!

Graham