View Full Version : Cumulative Month Header


cpower
2008-05-27, 05:41 AM
Hi all,

I'm currently evaluating OmniPlan and cannot seem to find out if I can do the following. When we map our projects we often do not have a start date for the proposal, so we plan from month 1 to month 36 for a 3 year project (for example). Is there a way I can get the header to do this on the task view?

Thanks,
Chris Power

Lizard
2008-05-27, 12:17 PM
Yes. In the project information inspector, you can change the Start from "On 5/29/08" (or whatever date it's set to) to "Undetermined Start Date". Then the task view will display the kind of labels you want.