PDA

View Full Version : Display effort as hours only?


sbjordal
2008-06-04, 09:49 AM
Is there a way to only show the task efforts as hours?

Right now, it would appear the effort and duration automatically converts to days and weeks, but for a project I have an interested in only displaying the effort as hours.

Is this possible?

Lizard
2008-06-04, 01:45 PM
You can customize what units are used for effort and duration, but you have to use the same units for both. The options are on the Project: Formatting inspector.

sbjordal
2008-06-05, 06:46 AM
That took care of it.