Start and Flagged combined?
Hello.
I have a system that's mostly working for me. I use Start Dates on about 30% of my tasks, so I can hide them until I need to see them. I only use Due Dates sparingly, for when stuff has a true deadline. And every day, I look at my list of undated tasks and Flag what I'd like to do. The only trouble is, for me to look at my "today" tasks, I need to use a Start perspective and a separate Flagged perspective. That's okay, but not optimal, as I usually forget to look at one while looking at the other. Would make sense to have one list. Anyone have a suggestion? Thanks, Robin |
Robin, just to make sure I'm understanding your request: you need a "task has started or is flagged" perspective?
|
[QUOTE=Brian;95748]Robin, just to make sure I'm understanding your request: you need a "task has started or is flagged" perspective?[/QUOTE]
That sounds right. I would ideally group on Started, so I could see what started today, and then filter on Started or is Flagged. Thanks. |
Not currently possible, I'm afraid, but we do have a feature request open on adding some additional start-date view filters which would make it possible. Folks who would like to see that added (including folks that read this thread later) should email the [EMAIL="omnifocus@omnigroup.com"]support ninjas[/EMAIL] and ask to be added to that feature request. Thanks!
|