Changing Weekends
 
I need to change when the weekends are in my Omniplan from Saturday/Sunday to Friday/Saturday. It is currently not letting me assign tasks on my work week of Sun-Thur, it will not let me assign a task on Sundays?

So, how do I change the actual work week from Mon-Fri to Sun-Thr?

Thanks!

lance

whpalmer4 2009-08-25 09:26 AM

2 Attachment(s)
First, go to the calendar view, select the Normal Work Week for Project setting at the lower left, and adjust the display on the right to show the dates and hours of a normal work week for this project. You can also do this on a per-resource and per-date basis to account for vacations, different schedules, etc.

Now when you level the project the dates should reflect your newly set schedule. See the attached example.

lspitzner 2009-08-25 10:00 AM

That did it, thanks so much! Omniplan rocks :)