lokner 2006-11-20 10:02 AM

Changing type
 
Today I was creating a new project plan and the first thing I always do is putting in the milestones (which were about 30). When you create a task by tapping the enter key it automatically creates a "task", so you could imagine my frustration when I had to manually change these into "milestone".

First, it would be nice to be able to set the standard type which is inserted when hitting Enter.

Second, why not move up "Type" in the menu which is seen when right-clicking an item? Yes, I'm too lazy to move my hand all the way down... ;)

skwirl 2006-11-28 03:37 PM

We have a feature request for keyboard shortcuts to change the task types.

I also entered a feature request for the ability to set your enter key to create a default task type of your choice, and about moving "Type" higher up in the contextual menu. :D