The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniPlan General (http://forums.omnigroup.com/forumdisplay.php?f=37)
-   -   Total Cost blank if assign task to resource group. (http://forums.omnigroup.com/showthread.php?t=2742)

gregc 2007-02-02 06:51 PM

Total Cost blank if assign task to resource group.
 
Hi all,

I've setup a group 'software dev team' with 4 members. I've allocated a cost/hour to each member. The cost/hour of the group is the average cost of each member. So far so good.

But if I assign the group to tasks with associated 'effort' values the 'total cost' column remains blank. if i associate the tast to an individual resource i get a correct calculation.

What am i doing wrong?

rdjong 2007-02-04 06:38 AM

I ran into the same problem and filed a bug report for it a few weeks ago. Apparently this is not yet solved in the 1.1 beta.

Tom Bunch 2007-02-06 11:15 AM

Thanks for the reports. It's in our database and we've got top men working on it.

-Tom

[SIZE="1"]"Who?" "Top... men."[/SIZE]