iCal Import doesn't recognize workday?
I just built a little test project with resources wherein I defined the work week as M-F 9-12 and 1-6. I then exported it to an .ics file and imported it into a calendar. My schedule items all run continuously 24 hours a day and don't seem to recognize my work week schedule as defined. What could I be missing?
|
How did you answer the question at the bottom of the Export... dialog about one event per task or work period?
|
[QUOTE=whpalmer4;92728]How did you answer the question at the bottom of the Export... dialog about one event per task or work period?[/QUOTE]
One event per task, did the other one and it works! Thanks for the clue. |