Assigned Resources
I have a question about resource assignment for a task.
Lets say I have a task called Painting and its effort is 1 day. I have two workers both working only between 8 am - 12 am. This, I set up in the Calendar view. The Normal week for the project though is 8am-12am, 1pm-17pm. Now I choose the task in Task View and assign the first worker to the task. In the Gant view I can see that the Duration goes from 1d to 1d 4 h. When I assign the next worker also to the task I can see that the Duration remains 1d 4h. I think this is strange. I have grayed out Duration so that it should not change (the two heads grayed out). I thought that Duration should not change even if I assign it to a person working only half a day. Perhaps I'm missing something? /rob :-) |