Changing resource allocation over time?
When setting up resources for a project, each resource's availability varies over time. For example, this month John can be allocated 50% to this project, but next month he can be allocated 75% to this project.
Is there a way to set this up in OmniPlan? - Tim |
Not at the moment. We have a feature request for this in our database so I'll add a vote for you. Right now you'll need to make a new task each time the resource allocation needs to change.
|
Please add a vote for me also
|