Planning consulting
 
I have to plan consulting task. I mean: contract terms include three months of consulting, one day a week. So I have to spend 12 days for this task, in 3 months. How can I configure tasks like this?

aboeing 2011-12-11 09:05 PM

Just edit the available time calendar, there is a video tutorial on this topic on the omniplan website.