julamoor 2007-06-13 08:44 AM

Can you remove time from start/end dates?
 
I work in an academic environment where time is very flexible. We need to track projects by days/weeks as opposed to time of day. Is there a way to disable or remove the time stamps from a project (i.e. start and end dates of a task)? They just add a layer of confusion that's not needed.

Thanks!

PS - love your products!

julamoor 2007-06-13 11:14 AM

Nevermind - figured it out. Preferences are very, very good things.

skwirl 2007-06-13 05:07 PM

[QUOTE=julamoor]Nevermind - figured it out. Preferences are very, very good things.[/QUOTE]

Glad to hear you got everything working. :-)

In case anyone else is curious, to remove the time from the start/end dates go to the "Project : Formatting" inspector and check off the "Time of Day" option.