Automatically assign a resource to new tasks?
Most of my projects have one resource - me.
Is there a way to automatically assign myself to each task on creation? I've tried assigning myself to a group in the hope that new subtasks would inherit the setting, but that doesn't seem to work. Is there another way? |
Yes there is! :-)
You can create a new task and assign yourself to it. Then, select that task and go to "Project" > "Set as Default for New Tasks". From now on, new tasks will have you assigned to it by default. |
Fantastic - I can change the default duration to 1hr too.
Thanks. |