Schengel 2009-09-01 05:08 AM

Reschedule an action
 
When I reschedule an action, because I could not finish the work, the rescheduled action is still shown at the old maturity when actions are sorted by the maturity. Is it a bug? What can I do that the rescheduled action is shown at the right maturity.

Thanks
Schengel

malisa 2009-09-01 05:21 AM

Are you changing the due date, the start date, or both?

Schengel 2009-09-01 08:46 AM

I'm changing the due date.

whpalmer4 2009-09-01 08:54 AM

If you are changing the due date on an action contained in a project which also has a due date, the project's due date will be used for display purposes if it is earlier than the action's. It isn't necessarily obvious that this is taking place, because you'll see the date you set for the action if you look in the due date column or the due date field in the inspector, but for the purposes of sorting the view, grouping the view, or styling the actions, the more restrictive due date will be used.

Schengel 2009-09-01 11:10 PM

Thanks. That's it. - UserUnableError-