Is it possible to display cumulative days along the X axis in the Gantt chart? I need to plan a project using cumulative days, rather than calendar days.
|
Not sure it's exactly what you're after, but this might help.
1) Open the Project: Information inspector 2) Change the Start: to "Undetermined Date" This will change the headings to things like "Day 17" and "Week 3" |
Great suggestion
Your suggestion will work. I had hoped to get cumulative days, but cumulative weeks works for my project. Thanks!
|
You can have cumulative days by zooming in more. Click the magnifying glass in the upper right corner of the Gantt chart and choose Days.
|