iamhim 2012-08-24 10:05 AM

Auto-assign resources
 
I have a list of few hundred tasks and bunch of resources. Since they all have same skill set, I am not too keen on which task is executed by whom. Is there a way to assign resources and come up with schedule without assigning resources individually. Round robin would be great, if possible.

jonwhite 2012-08-25 12:01 PM

Use a resource group
 
I think the answer to your problem is to use resource groups:[LIST=1][*]Create a group of resources.[*]Assign each task to the resource group.[/LIST]OmniPlan will assign each task to a member of the group.

iamhim 2012-08-27 08:54 PM

[QUOTE=jonwhite;113896]I think the answer to your problem is to use resource groups:[LIST=1][*]Create a group of resources.[*]Assign each task to the resource group.[/LIST]OmniPlan will assign each task to a member of the group.[/QUOTE]
Worked like charm. Thank you.