Overallocation of resources
 
Is there an easy way to show overallocation of resources? I understand the auto-leveling feature etc, but I'd rather do it consciously in reaction to seeing over allocations. I'm wondering if there is some way that I can get it to show up as a violation or something.

whpalmer4 2012-04-24 12:30 PM

Go to the resource view, click on the icon with three little bars of increasing height (underneath the Connection icon in the image below). Now anywhere you see a pink/red blob underneath a task in the right hand side of the window, you've got a resource being overcommitted. When the blue bar doesn't come all the way up to the middle line, you've got a resource being underutilized. If you don't select any of the resources on the left, the view on the right shows all of them, otherwise it only shows the selected resources.

[URL=http://imageshack.us/photo/my-images/338/screenshot20120424at127.png/][IMG]http://img338.imageshack.us/img338/6172/screenshot20120424at127.png[/IMG][/URL]

tmistretta 2012-04-24 01:40 PM

Cool
 
Thank you!!