Hours Worked ??
I am very new. I am working on a project that has some days that are normal days i.e.. 5 days a week at 8 hrs a day. At some point the days will change to a scenario where I will have three 8 hour shifts a day, each with 5 or six tasks.
How do I set up OmniPlan to see the two different kinds of days appropriately. Each time I try to adjust the times worked it seems to react globally, calculating the days worked. Tom |
I'm new to OP myself, but I imagine that putting your shifts in iCal and subscribing to it in OP would do the trick.
Ninjas, am I on the right track with this? |