Help with Resources, Using crews of people
1 Attachment(s)
Here is what I am trying to do.
I have a foreman "Austin F." he spends 50% of his time on foreman responsibilities. The other 50% is divided between crew 1 and 2. What do I need to enter in the Units and Efficiency boxes to make this all work out. I am also hoping that I can assign all the members of a crew by selecting the group they are in. Some of my crews are 15 people or better and selecting each one would take forever on a large job. Currently when I select the group the dialog says 1 of 2. Just to wrap it all up. I want to be able to select a task, click on the crew I want to accomplish that task, and have each member of that crew assigned to the task including the foreman for that crew at x% Thanks in advance. I have been going around in circles to the point I have muddied the water and can't see my way out. |
[QUOTE=twobarb;71041]Here is what I am trying to do.
I have a foreman "Austin F." he spends 50% of his time on foreman responsibilities. The other 50% is divided between crew 1 and 2. What do I need to enter in the Units and Efficiency boxes to make this all work out. [/QUOTE] You could create Austin F. as a resource with 100% units and when Austin is assigned to a foreman task you'll need to go to the Task : Assignment inspector and change the percentage to 50% of 100%. If Austin is assigned to a Crew 1 or 2 task, do the same thing but change Austin to 25% instead. [QUOTE=twobarb;71041] I am also hoping that I can assign all the members of a crew by selecting the group they are in. Some of my crews are 15 people or better and selecting each one would take forever on a large job. Currently when I select the group the dialog says 1 of 2. [/QUOTE] The group resource doesn't work this way currently. If you assign a group resource to a task it doesn't assign every resource to the task, it's supposed to automatically pick one available resource within a group for the task after you level the project. In other words, I need someone from my electrical team to look at this task ASAP but I don't care who, just let OmniPlan find the first resource from the electrical team and assign him/her to it. [QUOTE=twobarb;71041] Just to wrap it all up. I want to be able to select a task, click on the crew I want to accomplish that task, and have each member of that crew assigned to the task including the foreman for that crew at x% [/QUOTE] There isn't a way to do this now but I'll file a feature request for this in our database for consideration. |
All times are GMT -8. The time now is 01:28 PM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.