Planning a project with a limited number of days/month
I am planning a project whereby the company works 5 days a month on the project. Despite setting the day to 8 hours, and the month to 40 hours, the gantt shows many many more than 5 days worth of tasks starting at the same time, on day one.
Is there a way of telling the gantt to only allocate 5 days per month, and then move tasks to the next in order of priority and dependencies? Thanks |
In the calendar view, you can specify which days are actually working days for this project. Then OmniPlan will only schedule tasks on those days.
|
All times are GMT -8. The time now is 06:04 PM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.