-   -   Planning a project with a limited number of days/month (http://forums.omnigroup.com/showthread.php?t=8163)

Omni User 2008-06-12 08:03 AM

Planning a project with a limited number of days/month
 
I am planning a project whereby the company works 5 days a month on the project. Despite setting the day to 8 hours, and the month to 40 hours, the gantt shows many many more than 5 days worth of tasks starting at the same time, on day one.

Is there a way of telling the gantt to only allocate 5 days per month, and then move tasks to the next in order of priority and dependencies?

Thanks

Lizard 2008-06-12 10:23 AM

In the calendar view, you can specify which days are actually working days for this project. Then OmniPlan will only schedule tasks on those days.