How does lead time work?
I am a new OmniPlan user. I have two days left on my trial and I am almost sure I'm going to purchase, but have one question that having answer to would really help me decide.
Here's the example: Day 1: 1) Post ad Day 2: 2) Check on results day 1 Day 3: 3) Check on results day 2 I want the "Check on results" tasks to fall sometime on the next day. It doesn't matter exactly when, but they HAVE to be on the next day. I used the lead time "+1d" and OmniPlan still schedules the tasks for within the same day quite often (albeit with a large lead time). I really don't understand that. Any thoughts, comments, or suggestions would be much appreciated! Thanks in advance, Nathan |
Nathan, I didn't want you to think your question had gone unread, but I must confess that there are other folks at the company with stronger OmniPlan-fu than I possess...
We collectively browse the forums as we are able to do so, but if you need a guaranteed response, you're generally best off if you email the [EMAIL="omniplan@omnigroup.com"]support ninjas[/EMAIL]. |
All times are GMT -8. The time now is 12:56 AM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.