Newbie on OmniPlan here... tried to find an answer in the forums but didn't see it so please forgive me if this is obvious. I have 2 questions:

1) once you assign resources, can you hide them so they don't display the name, effort, etc... after the task in the Gantt chart?

2) Is there a way to display the task columns on each printed page next to the Gannt chart? (I can only get it to display and print on the 1st page and then the remaining pages only contain the Gantt.

Much thanks in advance,
sherie

Lizard 2008-06-04 08:46 AM

1) In OmniPlan 1.5, choose "View Options..." from the View menu to customize what text is displayed on the gantt view.
2) No. Consider using the "View Options..." to put the task name to the left or right of the gantt bar.

SMasters 2008-06-04 10:42 AM

Thank you! Of course, once I did what you recommended it was obvious. Duh on my part! Love OmniGraffle so hoping I can ramp on this quickly. Thanks again! (Have my first Gantt together for new client in a matter of hours here so ... so far, so good! Sure is nice not to have to boot up the Windows machine with MS Project!)