(Caution! New user - please be patient if the answer is obvious - I have looked in the manual and in this forum but couldn't find a good answer)
I'm looking for recommendations for how to represent a weekly meeting on my schedule. I realize I could put in a milestone for each week as a separate task, but I'd really like them to show all on one line instead of each meeting being on a separate line so that all of those items don't take up so much vertical space. If I group them and collapse the group, they don't show up as milestones - it shows as a continuous activity. Any suggestions? Julia |