Multiple time constraints?
I'd like to set up a task that doesn't have a duration or an effort, but instead is bounded at the beginning and at the end by dependencies on other tasks.
As an example, let's say I have a QA Testing task - it should start a little while after the start of Software Construction, and it should continue for as long as Software Construction (which is a group task) goes on. Is this possible? Is so, how? Thanks in advance, Scott |
I'm afraid not. Not directly, or in a way where you could assign resources to the QA Testing task.
One thing that you could do would be to make a QA Testing group with 2 milestones inside: Begin QA Testing (which would have a start-to-start dependency with some lag time on Software Construction), and End QA Testing (which would have a finish-to-start dependency on Software Construction). Then collapse the QA Testing group and it will have the correct start and end dates and duration. |
Thanks for the suggestion. Unfortunately the resource costs don't seem to be added if you do that (it lets you assign resources to a group but doesn't add their cost, presumably because the group itself has no real effort).
|