The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   Applying OmniFocus (http://forums.omnigroup.com/forumdisplay.php?f=51)
-   -   Perspectives Question: Today's Perspective using only tasks w/ due dates (http://forums.omnigroup.com/showthread.php?t=24603)

boogerus 2012-06-18 01:09 AM

Perspectives Question: Today's Perspective using only tasks w/ due dates
 
Hi There,

I would like to create a perspective that gives me the tasks I can do today organized by project (or by context) that includes only the tasks that I've given due dates. This will eliminate all the tasks that I've not yet given start dates - which is a pretty big list at the moment.

What I have done at the moment is a created a perspective set up like this:
Projects: remaining
Group projects by: start
Start projects by: start
Availability: remaining
Status: any status
Duration: any duration.

But this set up gives me both my tasks w/ dates and w/o dates.

I've read somewhere on the forums that a work around is to use flagging to eliminate the tasks w/o start dates. But that means I'll have to do a lot of flagging and I'd rather avoid this if possible.

Anyone know of a solution? Or maybe there is already a thread that I couldn't find?

If we need to add flagging then filter by flag, then I'd like to request a feature that allows filtering only those tasks w/ start dates.

Thanks for any insights you might have. I appreciate the forums and all the wisdom here.

Douglas

DrJJWMac 2012-06-18 04:50 AM

[QUOTE=boogerus;111672]
I would like to create a perspective ... that includes only the tasks that I've given due dates. ...

What I have done at the moment is a created a perspective set up like this:
Projects: remaining
Group projects by: start
Start projects by: start
Availability: remaining
Status: any status[/quote]

Status: Due

--
JJW


All times are GMT -8. The time now is 01:52 PM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.