mr_projects 2007-10-31 02:52 AM

[SOLVED] assigning efficiency values to tasks ?
 
Currently efficiency is assigned to a certain resource for the whole project, don't you think it could help adding an option to assign efficiency values on a task by task basis ?

vil 2007-10-31 04:57 AM

OmniPlan does this already. It copies the current efficiency value for the resource when you assign the resource to a task, but you can then edit it per task in the Task: Assignments inspector.

mr_projects 2007-10-31 06:41 AM

it only shows 100% of 100% , I don't see a way to change it

vil 2007-10-31 07:24 AM

Try clicking on that and typing...

mr_projects 2007-10-31 11:40 AM

aha ok, thanks its working now :)