Tasks are not changing as expected with leveling
I have a resource assigned to 6:30 pm to 9:30 pm schedule and another one with the same availability.
One task that requires both will take 3 hrs to complete, another will take 2 hrs. However, OmniPlan is scheduling the tasks for mid-afternoon starting at 2:30. This makes no sense. I've double checked assignments and schedules and re-leveled. Any ideas? Thanks in advance! |
Use Help->Send Feedback to send a desensitized version of your document to Omni, and tell them about the problem in terms of the task IDs (3.1, 5.2.6, etc.) so they can have a look.
|