chat-noir 2008-02-21 09:48 AM

Resource Time Fulfillment
 
Hi

Is there anyway of allocating a required time unit that a resource (staff) must fulfil. At the moment when putting in tasks my 'Staff' resources are always at 100%, but this figure is derived from the amount of tasks, not against the unit of time you have to allocate to them.

I.e. a milestone is 4 weeks and I need to ensure everyone is tasked up for the whole of the 4 weeks, and I would like Omniplan to flag when they are not.

At the moment, I have gaps in people's work schedules because of dependencies etc. and I have to look in detail to find these and there is no flag marking these areas out.

Thanks

chat-noir

Lizard 2008-02-21 12:01 PM

1 Attachment(s)
In the resource view, you can turn on the resource load graph. This will show green when a resource is fully booked, blue when they've got less than a full load, and pink when they're overloaded. You can turn this on by choosing "Show Resource Allocations" in the View menu, or clicking the icon shown in the attached screenshot.