The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniPlan General (http://forums.omnigroup.com/forumdisplay.php?f=37)
-   -   locking the start of a task immediately upon completion of the previous task (http://forums.omnigroup.com/showthread.php?t=5359)

mr_projects 2007-10-30 08:12 AM

locking the start of a task immediately upon completion of the previous task
 
This is probably one of my first threads here, I'm very happy with the overall usability of OmniPlan, I'm taking notes on suggestions/improvements very often along the way.

One of the features I'm looking for is locking the start of a subsequent task immediately upon completion of the previous task, so even leveling can't mess it up by making gaps between them.

My workaround behind this, is assigning a very high priority to both tasks, but a more convenient way is to be able to check a box somewhere in the inspector, like a "locked or solid F->S", any plans on implementing this feature ?

Thanks


All times are GMT -8. The time now is 04:23 AM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.