charlax 2011-11-03 10:36 AM

Reschedule incomplete tasks or increase task effort?
 
Hi!

I have a rather naive question. I'm monitoring a project and there seems to be two ways of updating a project schedule:

1- "Reschedule incomplete tasks" feature
2- Increase the tasks length (duration)

I'm not sure to fully understand the implication of those two possibilities.

What I don't like in option 1 is that tasks are split and it makes the planning less easy to read. Cf.:

Before

[IMG]https://img.skitch.com/20111103-cq4hg3twcfr9emintdu9m481di.jpg[/IMG]

After

[IMG]https://img.skitch.com/20111103-j195wwyp1ffib1ua2juncf661p.jpg[/IMG]

Thanks for your help!