Starting tasks together
I have several tasks that must start together or with an offset from each other. For instances:
Project Manage: Start Q1 Tech Lead: Start at same time as Project Manager. Software Development: Start 1 week after Tech Lead Database Development: Start at same time as Software ETL: Start at same time as Software The start constraints doesn't quite do it for me b/c it only ensures that Task B starts after Task A, but does not force them to start together. Is there a way to do this? |
Looking at the docs for the types of dependencies, its more clear to me what is missing: Required overlap.
All of the relations specify that tasks *may* overlap, but do not require it. So essentially the types F-F and S-S should allow a 'In Unison' option, which would require that the tasks either start together or end together (with the option of an offset as is currently supported). Some real world unison task examples: * Start together: Fly Plane & Co-Pilot Plane * Finish together: Cook Main Dish & Cook Side Dish to serve together. |
All times are GMT -8. The time now is 08:27 PM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.