The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniPlan General (http://forums.omnigroup.com/forumdisplay.php?f=37)
-   -   Rescheduling the Entire Project (http://forums.omnigroup.com/showthread.php?t=3818)

p_davis 2007-06-12 10:40 AM

Rescheduling the Entire Project
 
Hi folks:

As I have recently moved from a PC to Mac, I've just begun evaluating OminPlan and can't seem to figure out what should be simple.

Let's say I've entered all the tasks and duration info in a project, but now I want to start the project on a different day. Is there any way to select all the tasks and move them without messing with the dependency functions?

Thanks.

coconino 2007-06-12 12:31 PM

Select all tasks and then use Reschedule button (toolbar) or shift-cmd-R.

p_davis 2007-06-12 12:48 PM

[QUOTE=coconino]Select all tasks and then use Reschedule button (toolbar) or shift-cmd-R.[/QUOTE]
Thanks, but I've tried that. When I do it, ALL the tasks move to the new start date, except the first one that extends from the old start date to the new one. They do not keep their relative position.

Also, I can't seem to reschedule backwards - a date previous to the original start date.

Lizard 2007-06-12 01:11 PM

coconino: Reschedule is for when you've made your plan, and worked on it for a few weeks, then realize some tasks are behind schedule. It slides them forward so that their incomplete portions start on or after the current date.

p_davis: I think you really want the start date in the project information inspector. You can set a specific date, or use an "Unspecified Start Date", so times will be labeled "T + 1 day", "T + 2 months", etc.

p_davis 2007-06-12 01:30 PM

[QUOTE=Lizard]p_davis: I think you really want the start date in the project information inspector. You can set a specific date, or use an "Unspecified Start Date", so times will be labeled "T + 1 day", "T + 2 months", etc.[/QUOTE]
Thanks...but I need to work in real dates. Once I change to an unspecified date, I don't seem to be able to assign a new start date. Is there a way to do that?

Are you saying that tasks just can't simply be selected and moved keeping their relative position to eachother?

dejongj 2007-06-12 02:49 PM

How I normally do that is indeed by having predecessors defined (or dependencies as Omniplan calls them), that 1) allows for highlighting the critical path, but also when you have a milestone date that 'starts' it you only have to change that date and everything else gets 'rescheduled'...

I think that from a project management perspective that approach makes sense, as it is a pretty big decision to make to shift everything, so worthy of a mile-stone!

coconino 2007-06-13 03:07 AM

[QUOTE=Lizard]coconino: Reschedule is for when you've made your plan, and worked on it for a few weeks, then realize some tasks are behind schedule. It slides them forward so that their incomplete portions start on or after the current date.[/QUOTE]

Well, I didn't post without testing it and when I tested it it worked for me. I opened a plan which had no items completed, selected all, hit reschedule and picked a date. The plan moved to start on the new date, with all the dependencies and relationships intact. YMMV.

geoffc 2007-06-13 03:49 PM

Maybe with AppleScript?
 
[QUOTE=p_davis]Hi folks:
Let's say I've entered all the tasks and duration info in a project, but now I want to start the project on a different day. Is there any way to select all the tasks and move them without messing with the dependency functions?
[/QUOTE]

I'm not in front of my Mac right now, but you could probably do this with AppleScript, or possibly with Automator. It's not an ideal answer (more work than it should be) but it seems do-able.

p_davis 2007-06-14 06:10 AM

[QUOTE=geoffc]...you could probably do this with AppleScript, or possibly with Automator. It's not an ideal answer (more work than it should be) but it seems do-able.[/QUOTE]
LOL

Thanks, but when I'm evaluating software for purchase, that's the kind of phrase that tells me I need to move on!

countrymac 2007-06-14 11:31 AM

Must be possible to reschedule all
 
I am working on migration schedules across the globe and everything is focused on the DayOne date (which is the day the customers come in and work in the new environment).

All my tasks are leading up to this point.
So Task1 is -60days prior to DayOne, Task2 is -32days prior to DayOne, Task3 is -30 days prior to DayOne, etc...

I basically have been creating a template/group of tasks for each region (North America, Asia Pacific, Latin America, Europe) and then I copy those tasks for each branch we are migrating just changing the name and the DayOne date.

How can I get all my tasks to shift based just on the DayOne date changing?


All times are GMT -8. The time now is 12:21 PM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.