Inability to adjust for tasks that are completed ahead of schedule
I have exactly the same problem as this [URL="http://forums.omnigroup.com/showthread.php?t=1276&highlight=completed"]one[/URL], which is the inability to adjust for tasks that are completed ahead of schedule, meaning if i have three tasks:
A, B, C , and im doing task A right now: A ....B ........C but if B is done ahead of schedule, when leveling, it ought to look like this : A ....B ....C instead of not changing at all looks to me like its not differentiating between completed tasks and uncompleted ones, Thanks in Advance. |
That does sound like incorrect behavior. If task B is completed, and task C was delayed because it uses the same resource as task B, then it should be moved earlier. Oh, unless there's a dependency between task B and task C. If that's the case, you'll need to enter task B's actual completion date before task C will adjust the way you'd expect.
If you're still seeing something that smells like a bug, feel free to send an email to our ninjas at [email]omniplan@omnigroup.com[/email] |
2 Attachment(s)
I'd like to show an example, as well as the attached file
all tasks are attached together with F->S links, in this example B is 100% complete ahead of schedule, when leveling, it doesn't adjust C accordingly. I hope you got my point |
[QUOTE=mr_projects;23771]I'd like to show an example, as well as the attached file
all tasks are attached together with F->S links, in this example B is 100% complete ahead of schedule, when leveling, it doesn't adjust C accordingly. I hope you got my point[/QUOTE] In this situation, we'd recommend setting the end date of Task B to when it was completed. With the dependency connection between Task B and C, Task C won't start right after Task A because it has to start right after Task B's "Finish to Start" connection. If you remove the connection between Task B and Task C (provided that all tasks are assigned to the same resource), you'll see Task C being leveled to start right after Task A like you wanted it to. So for now, you should either change the end date of Task B or remove the dependency connection between Task B and Task C. I've filed a feature request in our database for an easier way to mark a task completed "today" and to automatically set the end date to reflect that. |
Im so thankful for your suppprt,
Im hoping there is a way to automatically remove the necessary dependencies when marking future tasks done Thanks, |