bgeipel 2007-11-02 06:47 PM

Leveling of short duration tasks
 
I tried to use OP to plan a rolled out web deployment and we had a large number of tasks that were each in the minute range. OP did no leveling of these tasks.

Any ideas what went wrong?

skwirl 2007-11-06 09:48 PM

[QUOTE=bgeipel;23907]I tried to use OP to plan a rolled out web deployment and we had a large number of tasks that were each in the minute range. OP did no leveling of these tasks.

Any ideas what went wrong?[/QUOTE]

Could you tell me what version of OmniPlan you're running and if possible, could you send in your project file to [email]omniplan@omnigroup.com[/email] for us to take a look at it?

Without seeing how your project is set up, I'm thinking your tasks either don't have any resources assigned to them (leveling doesn't balance tasks that have no resources), or you have your project granularity set to something other than "exact scheduling" in the "Project : Information" inspector.

bgeipel 2007-11-09 06:44 AM

Version: 1.1.2 (v131.9)

I have resources assigned

Cant find anything in the docs about "exact scheduling"

File sent

Thanks!

Lizard 2007-11-09 08:58 AM

"Exact scheduling" is the only option in 1.1.2. In 1.5 (which is in beta now), there's a new option to constrain scheduling to hour or day incrememnts.