Constraints visibility in Gantt chart
The release notes for beta 8 say "Added option to display/hide date constraints on the Gantt chart." as a new feature. How are constraints shown on the gantt chart? I've got a project with some start date constraints and the gantt looks the same visually no matter how many times I toggle View/Gantt Chart/Show-Hide Constraints. Any clues?
|
1 Attachment(s)
See the attached screenshot for some constraints. If the start date and constraint start date are exactly equal, the constraint is not going to be very visible.
|
Thanks! It would be great if there was an option in the Project:Colors inspector so that constraints could be made a little more visible.
|