"all day" option for the standard work week for the whole project
Are you going to support an "all day" option for the standard work week for the whole project ?
|
[QUOTE=mr_projects;23781]Are you going to support an "all day" option for the standard work week for the whole project ?[/QUOTE]
When you say "all day", do you mean 24 hours? The green bubbles in the work week are user configurable s all you have to do is drag them out so that they fill the entire day. Also, make sure you go to the "Project : Formatting" inspector and set the duration conversion factor to 24 hours = 1 day. |
dragging the bubble to fill the day worked for me, thanks
|