Can't add task before certain date
I purchased omniplan many months ago and stopped using because of date issue which i've forgotten about. today i started a project today and ran into the same problem again. this is my problem:
i created a plan with an ALAP of 8/23/2013 I created tasks building my way into ealier dates i can create tasks before 8/16/2013 if i try to set my project to ASAP, then all my tasks shift starting at 8/16 i don't understand why omni plan is fixated on stopping at 8/16/2013. i need this resolved, or i'll just move on again. thank you David Garcia |