tasks dependent on 2 resources avaliability
 
I have 2 resources. 1 is a staff member available 9 to 5pm the other is a computer available all the time. I then have a task which needs to be performed by this staff member on this computer. Omni plan assigns the work to happen overnight but the staff member is not available at that time. how do I assign a task to happen only when both resources are available?

Gizmo 2010-11-07 01:25 PM

bump....

whpalmer4 2010-11-07 01:49 PM

[QUOTE=Gizmo;88600]bump....[/QUOTE]

Gizmo, if you want a guaranteed response, you need to use the service with guaranteed responses :-) When you post a question here, you are mostly asking whatever Omni customers happen to read your post if they know the answer, and not asking anyone at Omni directly. Omni staffers do read the forum as time permits, but there's no guarantee (unlike with questions sent in via email to [email]omniplan@omnigroup.com[/email] or Help->Send Feedback) that someone will even see your post, much less respond.

I think the answer is that it cannot (conveniently) be done at the moment, judging from Aaron's post here: [url]http://forums.omnigroup.com/showpost.php?p=61083&postcount=4[/url]

Gizmo 2010-11-08 08:28 PM

thanks, I will use those services next time, cheers