-   -   Stop tasks readjusting after completing (http://forums.omnigroup.com/showthread.php?t=27174)

kaspa 2012-11-24 08:45 AM

Stop tasks readjusting after completing
 
Hi,

I have an issue I can't seem to figure out that keeps on blocking my further usage of OP in a project, I guess it's more of a lack of understanding issue than bug, here's the deal:

1. I have a list of tasks I need to do and they have each been estimated effort wise, just like here: http://cl.ly/image/3C1j1q0a452u

2. I assign resources to the tasks and they are automatically laid out to account for the resource load (as expected): http://cl.ly/image/2G2H2j2Z201N

3. I mark a task as complete, I would expect the task to be marked as completed (which indeed happens), however I'm not expecting the whole project plan to move forward (as if that task I just marked never existed) http://cl.ly/image/2Y3V362H143K

How can I prevent the tasks from readjusting after I complete them?

Best,
Kacper