nicopustil 2011-09-05 03:28 PM

Calendar
 
Hi I'm having a problem withe the working days.

Now it says saturday and sunday are working days and is taking wednesday and thursday as non working day. (that's when I click on extra and off hours view), when I click on normal hours the view shows two blocks from 8-12 hs and from 1 to 5 hs and working days from Monday to Friday so it's looks good as far as I can see.

Can anyone help me with this problem?

Thanks in advance

Nico

whpalmer4 2011-09-05 03:57 PM

Open up the OmniPlan preferences (under the OmniPlan menu bar item), click on the Display icon, check the setting for "Start weeks on:" and adjust if necessary.